Thursday 5 February 2015

Kitchen, Garage door and start of fixing

A few decent cosmetic changes have happened in the past week, with the garage door, kitchen cabinetry and the majority of the internal doors and fixing completed.

Garage all complete, all that's left is the up and down lights.

Kitchen coming along nicely with all cabinetry installed. Looking forward to the caesarstone benchtops and appliances to going in!


 Taken from the kitchen looking toward the living, happy with this too. This was taken at about 7.30pm at night, so it looks like the addition of the extra triple stacker and glass window splashback is letting a lot of natural light in!

All things are motoring along smoothly at this stage, with the only area of concern being that it appears our doors have been jimmied open.
This image is of the front door, while the garage entry looked to have the same markings on it. Not exactly too comforting as we have knowledge of a few break-ins in the estate during the build process. It won't hurt our pocket it anything happens, but just serve as an annoyance and cause delays! Fingers crossed this doesn't happen when the real front door is installed.

The build in general is absolutely flying along. We went for a look to see how the fixing was coming along this week, expecting to see most of the skirting done and that sort of thing and ended up looking at a garage door and a kitchen! We are due for our render to the frontage next week with internal painting, caesarstone and tiling next on the cards.

It seems Boutique will be well ahead of their advised handover date of May at this rate, which we expected, but to be at this point after the slab went down on the 5th of December is a great effort (taking in to account the Christmas break!).